We offer a 31 page manual that outlines each step of a typical installation. When you follow the basic steps in this manual, you will find the simple design is easy and fast to install. View the Installation Manual.
Field Measuring Guide
Because roofs slope up and down for drainage, the tubing for the RoofScreen frames must be cut to different lengths for each frame to keep the top of the wall level. We have a way of pre-cutting these tubes to length for you, eliminating the need to cut tubing on the roof. View more information about this process here.
Lead Times and Project Flow
For information about the steps and procedures required for a RoofScreen project, please see our Project Flow Chart.
Typical Lead Times
• Engineering and shop drawings take about 1 to 3 weeks depending on the complexity of the project.
• All of the component parts including the tubing are stocked at our facility in Santa Cruz, CA. and we can typically ship within one week of receiving an approved order.
• The panels are custom ordered by project and can take from 2 to 12 weeks depending on the type and finish of the panels ordered. |